Typical timelines
| Project type | Typical apps | Timeline |
|---|---|---|
| Small business | Accounting, Invoicing, Sales, basic Inventory | 4–8 weeks |
| Mid-size company | + Purchase, multi-warehouse, POS, e-invoicing, 1–2 integrations | 8–16 weeks |
| Multi-company or manufacturing | + MRP, consolidation, approvals, several integrations | 4–9 months |
The phases
- Discovery and design (15–20% of the effort): process workshops, a fit-gap list and a signed solution design.
- Configuration (30–40%): chart of accounts, taxes, journals, warehouses, routes, price lists, approvals and reports.
- Data migration (10–20%): master data and opening balances, loaded and reconciled twice, once to test and once for go-live.
- Testing and training (15–20%): end-to-end scenarios run by your own key users.
- Go-live and hypercare (10%): cut-over, the first month-end close, and fixes.
What drives effort and cost
- Customisation. Every custom module adds build, testing and upgrade cost. We use standard Odoo first and customise only where it pays back.
- Integrations, such as Shopify, Salla, banks, payment gateways and e-invoicing platforms.
- Data quality. Duplicate customers, wrong costs and unreconciled balances must be fixed before migration.
- Decision speed. One owner who can approve within three days saves weeks.
- Edition and hosting. Odoo Online, Odoo.sh or on-premise affects what you can customise and how upgrades work.
How to keep it on time
- Go live with the core apps first, then add the rest in phase 2.
- Migrate open items and balances, not years of transaction history.
- Close the first month in Odoo with your accountant before calling the project done.